Update on Building Progress in Balbriggan

June 18, 2016 0

Back in January and following up in April we brought you the story of a number of projects under construction in Balbriggan that were due for completion in 2016/2017.  Today, we are happy to bring you an update on the projects and to show you how work is progressing.  In just a few short months the building works have advanced and below are some updated photos taken today.

Bremore ETSS & Scoil Chormaic Community National School

building_progress_balbriggan_18jun16

New schools under construction off the Naul road to the west of Millfield Shopping centre for Bremore ETSS and Scoil Chormaic Community National School – Click here to view photo from April 2016

Primary Care Centre, Balbriggan

The opening of Balbriggan Primary Care Centre indicating the centre is due to open in the first quarter of 2017

building_progress_balbriggan_18jun16_2

New primary care centre in Balbriggan – Click here to view photo from April 2016

Castlemill Link Road

The surface is now on the Castlemill link road and it certainly looks like the road may open in the not too distant future.  This will certainly make life a lot easier traveling into the estates from the Naul road.

building_progress_balbriggan_18jun16_3

Castlemill Link Road – Click here to view photo from April 2016

Coláiste Ghlor na Mara

Northwest of the existing St. Georges National School, Off the Clonard Road (R122), Balbriggan, Co. Dublin.  The building comprises two construction phases. Phase two comprises of 1 no.2 storey extension of the school to accommodate 300 additional pupils, comprising teaching spaces and ancillary accommodation, with a floor area of C. 1890 sq.m. The total floor area for both phases is C. 9400 sq.m.

building_progress_balbriggan_18jun16_4

Coláiste Ghlor na Mara – Click here to view photo from April 2016